Luftaufnahme eines großen Industriekomplexes mit blauen Produktionshallen, hohen Schornsteinen und angrenzenden Betriebsflächen; das Werk liegt inmitten von Grünflächen und Wald unter klarem Himmel.

Rockwool Neuburg: Construction in Record Time – Despite the Pandemic

Conversion Under Full Operation

The project began inconspicuously on a gray February day in early 2018.

The two of us, Peter Struck and Moritz Bundschuh, drove to a new client to discuss geotechnical investigations and potentially provide further support. It quickly became clear that this project would be larger and more challenging than initially expected. The client was Rockwool, who wanted to comprehensively modernize a site while production was ongoing. The company produces, among other things, stone wool, which is used for insulation purposes.

The schedule was tight, the conditions demanding, and there was no lead time for the project. When asked whether we could start immediately, we had to swallow briefly – and then got going with full force. No sooner said than done: we submitted our references and met less than two weeks later with Rockwool’s newly installed project management in Copenhagen. The company’s goal was to start production with the new facilities in spring 2020. However, a production hall and its storage areas were still in operation on site. We had to operate on an open heart and also saw several challenges for Rockwool.

We asked Rockwool’s project manager whether they were aware that they would double production but also lose 80 percent of their storage space. They replied with a smile that it would actually be 100 percent of the storage space. At that point, it was clear that we understood each other. We began the conversion together with combined efforts. At the same time, we were competing with a sister project in the US. The rule was: whoever finished first would go into production. However, the sister project had a head start of six months.

We quickly took on the following tasks:

Geotechnical investigation and planning Demolition planning for buildings and storage areas Redesign, expansion, and modernization of existing storage areas and their more efficient use Finding partners for the client Developing and coordinating logistics concepts Creating and coordinating schedules without disrupting ongoing production Redesignating storage areas and integrating them with existing production Preparing and submitting permits, creating compensation areas Finalizing planning Preparing bills of quantities Conducting bidder discussions and selecting partners Managing the construction site And not least: communication, communication, communication

In December 2018, the time had come: the construction site was cleared, contracts were awarded, and in January 2019 the construction company began its work. By May, the first steel beams were in place. The topping-out ceremony for the first hall was held six weeks later. In October, the first halls were heated and installation of the equipment began. By February 2020, we were on the home stretch. Initial production test runs were successful. No one was talking about COVID yet.

In mid-March 2020, our Danish colleagues were suddenly no longer able to enter the country. The construction site quickly emptied, as the workers, mainly from Eastern Europe, understandably wanted to return to their families – preferably without having to spend two weeks in a quarantine camp. In the end, however, COVID was just another challenge that we were able to tackle and solve as a team.

English, German, and Danish were spoken on the construction site – yet communication worked. A certain amount of humor, as well as persistence, experience, innovation, and state-of-the-art technology, helped bring the project to a successful conclusion. From HPC AG’s side, we supported our colleagues in Denmark with regular drone flights, among other things. With a phone to our ear, we shared detailed photos of the construction site and reported on the progress of the work. We flexibly adapted the construction process to comply with COVID-19 regulations. For example, we completed outdoor facilities when the site was temporarily quiet due to partial lockdown.

In May 2020, we received the following message from our project manager, along with images of the first Rockwool produced at the new facility.

Message from the Project Manager

Hello everyone, I am very proud of what we have achieved in a short time in the NEU 9 project! Today’s production of the first wool is a milestone that we have all reached with great effort – and this result is based on excellent collaboration and brings us closer to the finish line. Testing in general, including the most demanding tests, will continue in the coming period. Let us use this great moment to gather the energy for the final sprint toward the handover to Rockwool GmbH. Please pass this appreciation on to everyone in your teams. Have a nice evening.

There is little to add to that: we are also proud of what has been achieved and look forward to the next steps in the project.

Client:
Rockwool
Project start:
Feb 2018
Project duration:
2 Years

Underground cabling: Ginger HPC as an advocate for soil and construction companies

The urgency of grid expansion to drive the energy transition has become particularly evident due to the Ukraine war. While…
Learn more

DNBA: The most cost-effective way to remediate groundwater and enable land use

Increasing scarcity of available land makes the redevelopment of abandoned sites—so-called brownfields—more important than ever. Industry and the real estate…
Learn more

Building between two water levels

Hamburg’s HafenCity is one of the most impressive urban development projects in the city: since 2001, an entirely new district…
Learn more

Following the water: General drainage plan for Meerbusch

The task was clear: the general drainage plan, now 20 years old, needed to be updated. Not only were there…
Learn more

In-situ: Removed as if by magic

Volatile halogenated hydrocarbons are difficult to remove from soil. Bernadette Bohnert and her team used an innovative method for contaminant…
Learn more

Rockwool Neuburg: Construction in Record Time – Despite the Pandemic

The project began inconspicuously on a gray February day in early 2018. The two of us, Peter Struck and Moritz…
Learn more

Minimizing Remediation Costs, Avoiding Dealbreakers: Working with TERQ-Based Remediation Plans

The number of undeveloped greenfield sites has declined significantly in recent years, bringing the conversion and reuse of decommissioned industrial…
Learn more

Federal Immission Control Act of Germany: Ginger HPC as translator

In the early 1970s, the German Federal Government presented its first environmental programme. The Federal Immission Control Act is intended…
Learn more

The vision for Kesslergrube: Germany’s ambitious remediation of a polluted area

Ambitious remediation of a polluted area instead of “out of sight, out of mind”. Ginger HPC AG is thoroughly remediating…
Learn more

Tracing Elmshorn’s Past – Between Historical Contaminated Sites and Modern Urban Redevelopment

The northern German city of Elmshorn is reinventing its center: a new town hall, new residential and commercial buildings, and…
Learn more

Award-Winning! Contaminated Site Remediation in Ulm

Following extensive investigations for unexploded ordnance, the contaminated soil will be removed using overlapping large-diameter boreholes down to 7 m…
Learn more

Lost rivers and the aftermath of war: Ginger HPC in Kosovo

Ginger HPC GmbH supports the development of knowledge and expertise in Kosovo – with the help of elaborately prepared workshops….
Learn more

Why work with us?

More than 75 years of experience

Since 1948, HPC has combined expertise and precision in environmental and engineering projects – ensuring reliable solutions that stand the test of time.

Strong international network

With offices across Europe and as a founding member of the INOGEN ALLIANCE, we bring global insights and local expertise to every project.

Award-winning sustainability

From international certifications to industry awards, our achievements reflect engineering precision, high standards, and a continuous drive for innovation.

Our Service Areas

Land Recycling

Land Recycling

Experience. Responsibility. Worldwide.

Life is constantly evolving. New buildings and installations are emerging on freely available land. Elsewhere occupied land is being redeveloped and…

Environment and Safety

Environment and Safety

Experience. Responsibility. Worldwide.

The environment and our living conditions determine our quality of life. Development entails changes. Sustainable environmental development is the…

Infrastructure

Infrastructure

Experience. Accountability. Valorisation.

Regional economic objectives of investment-related infrastructure policies can only be achieved by thorough infrastructure planning. Infrastructure…

Cookie Consent with Real Cookie Banner