Neu verlegte blaue Wasserleitungen mit Absperrarmaturen in einer Baugrube; die Rohre liegen im Kiesbett, darüber eine freigelegte Erdschicht und Baumaschinen im Hintergrund.

Back on Track: New Pipelines for Clean Water

Rehabilitation of the Wastewater Systems in Spittal/Drau

60 years that is roughly the service life of sewer systems. Why does that matter? When wastewater no longer flows properly, it can escape from the system and contaminants may enter the groundwater. This can have serious consequences for both people and the environment. To prevent this, the municipality of Spittal/Drau commissioned a comprehensive rehabilitation of its wastewater systems.

Precise preliminary work – the key to success
Under the direction of Ingenieurbüro Kronawetter GmbH (now HPC IBK), the entire combined sewer system was first examined, including pumping stations, combined sewer overflow structures and retention basins. This involved not only inspecting the existing sewer network but also measuring flow and precipitation volumes as well as assessing the impact on groundwater and surface water.

The result: significant hydraulic deficiencies had to be addressed immediately. Based on the hydraulic and structural assessment of the inspected sewers, the ecological situation and the possible future development of the system, a comprehensive rehabilitation plan was developed and implemented over a period of almost three years.

Implementation – Following the Path of the Sewers

Leaking and outdated sewer systems were rehabilitated using two different methods. In some sections, underground repairs were carried out using trenchless lining techniques (inliner method), which allow renewal within the existing pipes. In other areas, trenches were excavated and the pipes were completely replaced.

While these tasks themselves posed no difficulty for our experienced specialists, the team faced a very different challenge.

Clean into the Future

After only three years of planning and implementation, parts of the sewer system in Spittal/Drau are now operating like new again. The system has been upgraded to the latest state of the art and is therefore more sustainable than ever before.

No wastewater can enter the groundwater anymore, and in the long term the municipality will benefit from reduced operating and maintenance costs. Once again, our team has demonstrated that we combine technical expertise with a strong focus on sustainability.

The major challenge in this project lay in the extremely limited space and accessibility on site. In the western and eastern construction areas, the new daycare center building directly borders neighboring buildings that are still under construction. To the north and south, the excavation pit directly adjoins public spaces: on one side there is a tartan running track where neither construction vehicles can drive nor building materials can be stored. On the other side, the only access to the construction site is a one-way street with adjacent cycling and pedestrian paths. This means that extensive work, such as excavation, had to be organized under one-way traffic conditions.

This created major logistical challenges, not least when installing the water treatment plant required for groundwater lowering. Since there was very little space available around the excavation pit, the plant was installed 250 meters away on a plot of land where construction had not yet begun. A complex task in whose planning and implementation Ginger HPC was involved. In doing so, we made a significant contribution to preventing contamination of the Elbe River and the groundwater.

In the meantime, buoyancy protection for the new building is ensured by its own weight and additional structural load. As a result, the groundwater management system has been successfully completed and dismantled.

And Now? Moving into the Future with Sustainability

The space along the sides of the excavation pit is available for backfilling. It is planned to fill the southern shoring area, under the professional supervision of Ginger HPC, with flowable fill (liquid soil) up to 1.5 m below ground level. The sandy backfill to be placed above will be flushed in with water. During this process, the timber lagging will be gradually removed.

Finally, the public areas such as roads, pedestrian and cycle paths, as well as infrastructure including sewer lines for wastewater and stormwater, will be inspected through comprehensive elevation surveys, compaction tests and CCTV inspections of the pipelines. GingerHPC plans and initiates the required evidentiary safeguarding measures, carries out some of them directly, and evaluates the results.

Client:
Municipality of Spittal an der Drau
Project duration:
3 Years
Project location:
Austria

The project remains an exciting one for Ginger HPC. Following the successful excavation of the construction pit, structural construction works are now in full progress. Our team of experienced engineers continues to support the project with expert advice on geotechnical and environmental matters.

One of the next tasks will be the dismantling of the excavation support system, which consists of a braced Berlin-type shoring system on the north side and a double-anchored Essen-type shoring system on the south side. Extremely tight space conditions in the area alongside the excavation pit—locally only about 10 cm between the new building and the soldier pile shoring—pose particular challenges, especially on the south side, when backfilling the approximately 5-metre-deep space.

Underground cabling: Ginger HPC as an advocate for soil and construction companies

The urgency of grid expansion to drive the energy transition has become particularly evident due to the Ukraine war. While…
Learn more

DNBA: The most cost-effective way to remediate groundwater and enable land use

Increasing scarcity of available land makes the redevelopment of abandoned sites—so-called brownfields—more important than ever. Industry and the real estate…
Learn more

Building between two water levels

Hamburg’s HafenCity is one of the most impressive urban development projects in the city: since 2001, an entirely new district…
Learn more

Following the water: General drainage plan for Meerbusch

The task was clear: the general drainage plan, now 20 years old, needed to be updated. Not only were there…
Learn more

In-situ: Removed as if by magic

Volatile halogenated hydrocarbons are difficult to remove from soil. Bernadette Bohnert and her team used an innovative method for contaminant…
Learn more

Rockwool Neuburg: Construction in Record Time – Despite the Pandemic

The project began inconspicuously on a gray February day in early 2018. The two of us, Peter Struck and Moritz…
Learn more

Minimizing Remediation Costs, Avoiding Dealbreakers: Working with TERQ-Based Remediation Plans

The number of undeveloped greenfield sites has declined significantly in recent years, bringing the conversion and reuse of decommissioned industrial…
Learn more

Federal Immission Control Act of Germany: Ginger HPC as translator

In the early 1970s, the German Federal Government presented its first environmental programme. The Federal Immission Control Act is intended…
Learn more

The vision for Kesslergrube: Germany’s ambitious remediation of a polluted area

Ambitious remediation of a polluted area instead of “out of sight, out of mind”. Ginger HPC AG is thoroughly remediating…
Learn more

Tracing Elmshorn’s Past – Between Historical Contaminated Sites and Modern Urban Redevelopment

The northern German city of Elmshorn is reinventing its center: a new town hall, new residential and commercial buildings, and…
Learn more

Award-Winning! Contaminated Site Remediation in Ulm

Following extensive investigations for unexploded ordnance, the contaminated soil will be removed using overlapping large-diameter boreholes down to 7 m…
Learn more

Lost rivers and the aftermath of war: Ginger HPC in Kosovo

Ginger HPC GmbH supports the development of knowledge and expertise in Kosovo – with the help of elaborately prepared workshops….
Learn more

Why work with us?

More than 75 years of experience

Since 1948, HPC has combined expertise and precision in environmental and engineering projects – ensuring reliable solutions that stand the test of time.

Strong international network

With offices across Europe and as a founding member of the INOGEN ALLIANCE, we bring global insights and local expertise to every project.

Award-winning sustainability

From international certifications to industry awards, our achievements reflect engineering precision, high standards, and a continuous drive for innovation.

Our Service Areas

Land Recycling

Land Recycling

Experience. Responsibility. Worldwide.

Life is constantly evolving. New buildings and installations are emerging on freely available land. Elsewhere occupied land is being redeveloped and…

Environment and Safety

Environment and Safety

Experience. Responsibility. Worldwide.

The environment and our living conditions determine our quality of life. Development entails changes. Sustainable environmental development is the…

Infrastructure

Infrastructure

Experience. Accountability. Valorisation.

Regional economic objectives of investment-related infrastructure policies can only be achieved by thorough infrastructure planning. Infrastructure…

Cookie Consent with Real Cookie Banner